Please download the following documents, then follow the 'Demolition CDC Application Process' described below to submit your demolition CDC application to us via the NSW Planning Portal.
The Certification Contract must be completed and emailed back to us before lodging your CDC application via NSW Planning Portal.
Guidance Notes:
Important Information:
Required Documents:
Additional documents: (if applicable)
Please Note:
⚠️ Regional Exemption:
This written notice requirement does not apply in Wollongong, Shoalhaven, Shellharbour, Central Coast, Newcastle and most regional NSW LGAs. In these areas, your CDC may be determined immediately once all other requirements are satisfied.
Upon the issuing of a Complying Development Certificate, you will receive:
As required, we will also register a copy of the determination & all associated CDC documentation with Council via NSW Planning Portal, and with other Government agencies where required by NSW legislation.
⚠️ Critical Note on Owner's Consent:
A Complying Development Certificate is issued, subject to legislated conditions that must be complied with, prior to, and until completion of the demolition works.
CDC conditions include requirements for ensuring that site and environmental protections are in place prior to commencement of demolition works, and that they are maintained up until completion of the works. Site control measure include installation of site fencing, contractor/asbestos removal signage, and erosion & sediment control devices.
It is critical that Applicants, Owners & Contractors carefully read and understand all conditions of the Complying Development Certificate.
Notification Requirements:
⚠️ Notification to Neighbours of Intention to Commence Demolition Works:
As a condition of a CDC, owners must provide written notice to certain neighbours before demolition begins:
⚠️ Asbestos Removal Notifications:
If asbestos removal forms part of the demolition works, your demolition contractor must issue a separate written notices in accordance with the Work Health and Safety Regulation 2017.
Demolition work authorised under the Complying Development Certificate may only commence once:
Demolition work must comply with:
⚠️ Environmental Protection
It is critical to install and maintain effective erosion and sediment controls on site. Councils and the NSW EPA have powers under the Protection of the Environment Operations Act 1997 to impose significant penalties where controls are missing or inadequate.
⚠️ Requirements for Protected Trees
A separate Council approval is required to be obtained prior to pruning or removal of any protected trees.
To save you time and ensure compliance with the neighbour notification requirements of cl.148 of the EP & A Regulations 2021, we can prepare & post the owners 'Notice of Commencement' letters to the relevant neighbours on your behalf.
We post these 'Notice of Commencement' letters via an Australia Post mailing house ensuring that a time/date stamped postage record is maintained to confirm that the process has been completed at least 7 full days prior to commencement of the demolition works.
To give you peace of mind, our Certifiers can carry out a post-demolition site inspection to verify compliance with the conditions of the CDC.
Following a site inspection, we will provide an inspection report and can provide you with a letter if required by your builder or Council confirming that the demolition works have been completed.
Note: Separate advice from a suitably qualified consultant is required in relation to matters involving asbestos or contaminated land.
To save you the time consuming process of dealing with your local Council, our Certifiers can assist you with the process of having your swimming pool removed from the NSW Swimming Pool Register.
We will carry out a post-demolition inspection to verify compliance with the conditions of the demolition CDC and to confirm that the swimming pool has been removed.
Once the inspection has been carried out, our Certifiers have access to the NSW Swimming Pool Register and will be able to remove your pool from the Register.
Copyright © 2026 Home Building Certifiers Pty Ltd - All Rights Reserved.
ACN 640 411 776 | ABN 19 640 411 776
Liability limited by a scheme approved under Professional Standards Legislation.
www.HomeBuildingCertifiers.com.au
This website uses cookies for Google Analytics. By continuing to use this site, you accept our use of cookies.